  • Construction Updates

    Lanes & Streets

    • Open
      • Three WB Lanes from Garfield to Utica Park Blvd
      • Two right WB lanes from Utica Park Blvd up to and over M-53 bridge
    • Closed
      • Oleander at M-59
      • Colony, part-width
      • Dalcoma, part-width, NB to M-59. (SB open)
      • Woodridge, scheduled to close Thursday, April 27 for 14 days. Access will be maintained through the two adjacent streets, Westbrook and Eastbrook
      • Delco, part-width, scheduled to close April 29
      • Three WB Lanes from Garfield to Utica Park Blvd
      • Two right WB lanes from Utica Park Blvd up to and over M-53 bridge
    • Daytime
      • Open–three EB lanes in construction zone
      • Open–three WB lanes from Garfield to Utica Park Blvd, then 3 lanes merge into two right lanes up to and over the bridge
      • Electrical and more earthwork continues in median throughout the week
      • New temporary signals put in service and pothole patching continues
    • Nighttime
      • Open–from 9 pm to 6 am, two EB and two WB lanes remain open to accommodate work in median from Utica Park Blvd to Garfield
      • Open: Two EB right lanes are closed starting at Old Van Dyke Road and over the bridge through April

     
    M-59 Bridge Over M-53

    • Lanes shifted
      • EB M-59 bridge over M-53 have shifted leaving two left lanes open
    • Open/closed lanes
      • Work on WB M-59 bridge over M-53 will close two lanes and leave two lanes open
    • Ramp closed/detour
      • When WB M-59 lanes close, the ramp from west M-59 to south M-59 will close
      • Detour TBD: WB M-59 to median turnaround to east M-59 and south M-53

     
    Driveways

    • Part-width Driveway Closures*
      • Monday, May 1st
        • Chili’s –Access from the DXL/Dick’s Sporting Goods entrance will be maintained. Timeframe: four weeks
        • Grand Azteca – Timeframe: four weeks
        • Lakeside Budget Storage – Timeframe: four weeks
        • Diversity Business Solutions/Law Offices – Timeframe: four weeks
    • Full Driveway Closures
      • Monday, May 1st
        • Business Plaza on SW corner of M-59/Hayes – Timeframe: two weeks

    *Part-width means in and out access of the driveway is maintained. Full closure means the driveway is closed and access is maintained through another entrance.